Timeline

Nov 2016

Land Agreement

ACE develops exclusivity agreement on the use of the land from Bristol City Council which is ultimately signed in 2021.

Arrow Down

Aug 2019

Grid Connection Secured

ACE secure a grid connection agreement with Western Power Distribution for an 11kV supply to the turbine site. The works include the provision and installation of HV cable and substation equipment. 

Arrow Down

July 2020

Planning Approval Granted

On the 8th July 2020, ACE’s planning application, supported by comprehensive and detailed Environmental, Ecological, Transport, and Community reports, receives a unanimous vote for approval from Bristol City Council’s Planning Committee. The turbine approved has a maximum tip height of 150m. It is to be built on Council land at the site shown. The permission is granted for 25 years from commissioning. 

Arrow Down

Nov 2021

Planning Conditions Met

Pre-construction planning conditions are met and approved by Bristol City Council, thus allowing the project to progress.

Arrow Down

April
2022

Financial Close

The wind turbine receives funding from Thrive Renewables, Bristol & Bath Regional Capital, other local lenders, and a £0.5m grant from WECA via the European Bank for Reconstruction and Development. 

Arrow Down

July 2022

Groundwork Commences

Work begins on site with clearance and the development of access roads.

Arrow Down

Sept 2022

Foundation Works Begin

A steel rebar frame is used to shape a solid concrete foundation for the turbine.

Arrow Down

Feb 2023

Blades and Tower Delivered

Two weeks after arriving in the UK, the three blades are delivered to the site with a police escort. The tower sections arrive two days later.

Arrow Down

Feb 2023

Tower, Nacelle and Rotor Assembly

Following set up of the specialist crane, the tower sections are assembled and the nacelle and rotor are added over a four day period.

Arrow Down

Feb
2023

Blade Installation

It then takes a further week to install all three of the blades.

Arrow Down

March
2023

Commissioning

The commissioning process then begins to ensure the turbine is in working order.